TY - GEN A1 - Borndörfer, Ralf A1 - Erol, Berkan A1 - Graffagnino, Thomas A1 - Schlechte, Thomas A1 - Swarat, Elmar T1 - Optimizing the Simplon Railway Corridor N2 - This paper presents a case study on a railway timetable optimization for the very dense Simplon corridor, a major railway connection in the Alps between Switzerland and Italy. Starting from a detailed microscopic network as it is used in railway simulation, the data is transformed by an automatic procedure to a less detailed macroscopic network, that is sufficient for the purpose of capacity planning and amenable to state-of-the-art integer programming optimization methods. In this way, the macroscopic railway network is saturated with trains. Finally, the corresponding timetable is re-transformed to the microscopic level in such a way that it can be operated without any conflicts among the slots. Using this integer programming based micro-macro aggregation-disaggregation approach, it becomes for the first time possible to generate a profit maximal and conflict free timetable for the complete Simplon corridor over an entire day by a simultaneous optimization of all trains requests. This also allows to to undertake a sensitivity analysis of various problem parameters. T3 - ZIB-Report - 10-24 KW - Trassenallokation KW - Netzwerkaggregation KW - Fallstudie KW - Simplon Korridor KW - railway track allocation KW - network aggregation KW - case study KW - Simplon corridor Y1 - 2010 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-11892 SN - 1438-0064 ER - TY - GEN A1 - Borndörfer, Ralf A1 - Schlechte, Thomas A1 - Weider, Steffen T1 - Railway Track Allocation by Rapid Branching N2 - The track allocation problem, also known as train routing problem or train timetabling problem, is to find a conflict-free set of train routes of maximum value in a railway network. Although it can be modeled as a standard path packing problem, instances of sizes relevant for real-world railway applications could not be solved up to now. We propose a rapid branching column generation approach that integrates the solution of the LP relaxation of a path coupling formulation of the problem with a special rounding heuristic. The approach is based on and exploits special properties of the bundle method for the approximate solution of convex piecewise linear functions. Computational results for difficult instances of the benchmark library TTPLIB are reported. T3 - ZIB-Report - 10-22 KW - Trassenallokationsproblem KW - Ganzzahlige Programmierung KW - Rapid-Branching-Heuristik KW - Proximale Bündelmethode KW - Optimization KW - Railway Track Allocation KW - Bundle Method KW - Rapid Branching Y1 - 2010 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-11864 SN - 1438-0064 ER - TY - GEN A1 - Borndörfer, Ralf A1 - Karbstein, Marika T1 - Metric Inequalities for Routings on Direct Connections N2 - We consider multi-commodity flow problems in which capacities are installed on paths. In this setting, it is often important to distinguish between flows on direct connection routes, using single paths, and flows that include path switching. We show that the concept of metric inequalities to characterize capacities that support a multi-commodity flow can be generalized to deal with direct connections. T3 - ZIB-Report - 14-04 KW - metric inequalities KW - direct connection KW - multi-commodity flow problem Y1 - 2014 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-44219 SN - 1438-0064 ER - TY - GEN A1 - Borndörfer, Ralf A1 - Hoppmann, Heide A1 - Karbstein, Marika T1 - A Configuration Model for the Line Planning Problem N2 - We propose a novel extended formulation for the line planning problem in public transport. It is based on a new concept of frequency configurations that account for all possible options to provide a required transportation capacity on an infrastructure edge. We show that this model yields a strong LP relaxation. It implies, in particular, general classes of facet defining inequalities for the standard model. T3 - ZIB-Report - 13-40 KW - combinatorial optimization KW - polyhedral combinatorics KW - line planning Y1 - 2013 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-41903 SN - 1438-0064 ER - TY - GEN A1 - Heismann, Olga A1 - Hildenbrandt, Achim A1 - Silvestri, Francesco A1 - Reinelt, Gerhard A1 - Borndörfer, Ralf T1 - HUHFA: A Framework for Facet Classification N2 - Usually complete linear descriptions of polytopes consist of an enormous number of facet-defining inequalities already for very small problem sizes. In this paper, we describe a method for dividing the inequalities into equivalence classes without resorting to a normal form. Within each class, facets are related by certain symmetries and it is sufficient to list one representative of each class to give a complete picture of the structural properties of a polytope. We propose an algorithm for the classification and illustrate its efficiency on a broad range of combinatorial optimization problems including the Traveling Salesman and the Linear Ordering Problem. T3 - ZIB-Report - 13-45 KW - facet classification KW - symmetry KW - polyhedral structure Y1 - 2013 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-42230 SN - 1438-0064 ER - TY - THES A1 - Helmberg, Christoph T1 - Semidefinite Programming for Combinatorial Optimization N2 - This book offers a self-contained introduction to the field of semidefinite programming, its applications in combinatorial optimization, and its computational methods. We equip the reader with the basic results from linear algebra on positive semidefinite matrices and the cone spanned by them. Starting from linear programming, we introduce semidefinite programs and discuss the associated duality theory. We then turn to semidefinite relaxations of combinatorial optimization and illustrate their interrelation. In the second half we deal with computational methods for solving semidefinite programs. First, the interior point approach, its iteration complexity, and implementational issues are discussed. Next, we explain in great detail the spectral bundle method, which is particularly suited for large scale semidefinite programming. One of the most successful techniques in integer linear programming is the cutting plane approach which improves an initial relaxation by adding violated inequalities. We explore possibilities to combine the two solution methods with the cutting plane approach in order to strengthen semidefinite relaxations of combinatorial optimization problems. T3 - ZIB-Report - 00-34 KW - positive semidefinite matrices KW - semidefinite cone KW - semidefinite Programming KW - semidefinite duality KW - combinatorial optimization KW - max-cut KW - quadrati Y1 - 2000 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-6022 ER - TY - THES A1 - Martin, Alexander T1 - Integer Programs with Block Structure N2 - In this thesis we study and solve integer programs with block structure, i.\,e., problems that after the removal of certain rows (or columns) of the constraint matrix decompose into independent subproblems. The matrices associated with each subproblem are called blocks and the rows (columns) to be removed linking constraints (columns). Integer programs with block structure come up in a natural way in many real-world applications. The methods that are widely used to tackle integer programs with block structure are decomposition methods. The idea is to decouple the linking constraints (variables) from the problem and treat them at a superordinate level, often called master problem. The resulting residual subordinate problem then decomposes into independent subproblems that often can be solved more efficiently. Decomposition methods now work alternately on the master and subordinate problem and iteratively exchange information to solve the original problem to optimality. In Part I we follow a different approach. We treat the integer programming problem as a whole and keep the linking constraints in the formulation. We consider the associated polyhedra and investigate the polyhedral consequences of the involved linking constraints. The variety and complexity of the new inequalities that come into play is illustrated on three different types of real-world problems. The applications arise in the design of electronic circuits, in telecommunication and production planning. We develop a branch-and-cut algorithm for each of these problems, and our computational results show the benefits and limits of the polyhedral approach to solve these real-world models with block structure. Part II of the thesis deals with general mixed integer programming problems, that is integer programs with no apparent structure in the constraint matrix. We will discuss in Chapter 5 the main ingredients of an LP based branch-and-bound algorithm for the solution of general integer programs. Chapter 6 then asks the question whether general integer programs decompose into certain block structures and investigate whether it is possible to recognize such a structure. The remaining two chapters exploit information about the block structure of an integer program. In Chapter 7 we parallelize parts of the dual simplex algorithm, the method that is commonly used for the solution of the underlying linear programs within a branch-and-cut algorithm. In Chapter 8 we try to detect small blocks in the constraint matrix and to derive new cutting planes that strengthen the integer programming formulation. These inequalities may be associated with the intersection of several knapsack problems. We will see that they significantly improve the quality of the general integer programming solver introduced in Chapter 5. T3 - ZIB-Report - SC-99-03 KW - integer programming KW - cutting planes KW - block structure Y1 - 1999 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-3911 ER - TY - GEN A1 - Bley, Andreas T1 - An Integer Programming Algorithm for Routing Optimization in IP Networks N2 - Most data networks nowadays use shortest path protocols to route the traffic. Given administrative routing lengths for the links of the network, all data packets are sent along shortest paths with respect to these lengths from their source to their destination. In this paper, we present an integer programming algorithm for the minimum congestion unsplittable shortest path routing problem, which arises in the operational planning of such networks. Given a capacitated directed graph and a set of communication demands, the goal is to find routing lengths that define a unique shortest path for each demand and minimize the maximum congestion over all links in the resulting routing. We illustrate the general decomposition approach our algorithm is based on, present the integer and linear programming models used to solve the master and the client problem, and discuss the most important implementational aspects. Finally, we report computational results for various benchmark problems, which demonstrate the efficiency of our algorithm. T3 - ZIB-Report - 08-30 KW - Shortest Path Routing KW - Integer Programming Y1 - 2008 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-10814 SN - 1438-0064 ER - TY - GEN A1 - Schlechte, Thomas A1 - Borndörfer, Ralf T1 - Balancing Efficiency and Robustness – A Bi-criteria Optimization Approach to Railway Track Allocation N2 - Technical restrictions and challenging details let railway traffic become one of the most complex transportation systems. Routing trains in a conflict-free way through a track network is one of the basic scheduling problems for any railway company. This article focuses on a robust extension of this problem, also known as train timetabling problem (TTP), which consists in finding a schedule, a conflict free set of train routes, of maximum value for a given railway network. However, timetables are not only required to be profitable. Railway companies are also interested in reliable and robust solutions. Intuitively, we expect a more robust track allocation to be one where disruptions arising from delays are less likely to be propagated causing delays of subsequent trains. This trade-off between an efficient use of railway infrastructure and the prospects of recovery leads us to a bi-criteria optimization approach. On the one hand we want to maximize the profit of a schedule, that is more or less to maximize the number of feasible routed trains. On the other hand if two trains are scheduled as tight as possible after each other it is clear that a delay of the first one always affects the subsequent train. We present extensions of the integer programming formulation in [BorndoerferSchlechte2007] for solving (TTP). These models can incorporate both aspects, because of the additional track configuration variables. We discuss how these variables can directly be used to measure a certain type of robustness of a timetable. For these models which can be solved by column generation techniques, we propose so-called scalarization techniques, see [Ehrgott2005], to determine efficient solutions. Here, an efficient solution is one which does not allow any improvement in profit and robustness at the same time. We prove that the LP-relaxation of the (TTP) including an additional $\epsilon$-constraint remains solvable in polynomial time. Finally, we present some preliminary results on macroscopic real-world data of a part of the German long distance railway network. T3 - ZIB-Report - 08-22 KW - Train Timetabling Problem KW - Bicriteria Optimization KW - Column Generation Y1 - 2008 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-10763 SN - 1438-0064 ER - TY - GEN A1 - Erol, Berkan A1 - Klemenz, Marc A1 - Schlechte, Thomas A1 - Schultz, Sören A1 - Tanner, Andreas T1 - TTPLIB 2008 - A Library for Train Timetabling Problems N2 - We introduce (TTPlib), a data library for train timetabling problems that can be accessed at http://ttplib.zib.de. In version 1.0, the library contains data related to 50 scenarios. Most instances result from the combination of macroscopic railway networks and several train request sets for the German long distance area containing Hannover, Kassel and Fulda, short denoted by Ha-Ka-Fu. In this paper, we introduce the data concepts of TTPlib, describe the scenarios included in the library and provide a free visualization tool TraVis. T3 - ZIB-Report - 08-19 KW - Fahrplanung KW - Problembibliothek KW - Optimierung KW - Train Timetabling Problem KW - Data Library KW - Optimization Y1 - 2008 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-10732 SN - 1438-0064 ER - TY - GEN A1 - Borndörfer, Ralf A1 - Neumann, Marika A1 - Pfetsch, Marc T1 - The Line Connectivity Problem N2 - This paper introduces the "line connectivity problem", a generalization of the Steiner tree problem and a special case of the line planning problem. We study its complexity and give an IP formulation in terms of an exponential number of constraints associated with "line cut constraints". These inequalities can be separated in polynomial time. We also generalize the Steiner partition inequalities. T3 - ZIB-Report - 08-31 KW - Steiner Tree Generalization Y1 - 2008 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-10820 SN - 1438-0064 ER - TY - GEN A1 - Berthold, Timo A1 - Heinz, Stefan A1 - Pfetsch, Marc T1 - Solving Pseudo-Boolean Problems with SCIP N2 - Pseudo-Boolean problems generalize SAT problems by allowing linear constraints and a linear objective function. Different solvers, mainly having their roots in the SAT domain, have been proposed and compared,for instance, in Pseudo-Boolean evaluations. One can also formulate Pseudo-Boolean models as integer programming models. That is,Pseudo-Boolean problems lie on the border between the SAT domain and the integer programming field. In this paper, we approach Pseudo-Boolean problems from the integer programming side. We introduce the framework SCIP that implements constraint integer programming techniques. It integrates methods from constraint programming, integer programming, and SAT-solving: the solution of linear programming relaxations, propagation of linear as well as nonlinear constraints, and conflict analysis. We argue that this approach is suitable for Pseudo-Boolean instances containing general linear constraints, while it is less efficient for pure SAT problems. We present extensive computational experiments on the test set used for the Pseudo-Boolean evaluation 2007. We show that our approach is very efficient for optimization instances and competitive for feasibility problems. For the nonlinear parts, we also investigate the influence of linear programming relaxations and propagation methods on the performance. It turns out that both techniques are helpful for obtaining an efficient solution method. T3 - ZIB-Report - 08-12 KW - Pseudo-Boolean KW - Constraint Programming KW - Ganzzahlige Programmierung KW - Branch-And-Cut KW - Optimierungssoftware KW - Pseudo-Boolean KW - constraint integer programming KW - integer programming KW - branch-and-cut KW - optimization software Y1 - 2008 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-10671 SN - 1438-0064 ER - TY - GEN A1 - Borndörfer, Ralf A1 - Neumann, Marika A1 - Pfetsch, Marc T1 - Angebotsplanung im öffentlichen Nahverkehr T1 - Service Design in Public Transport N2 - Die Angebotsplanung im öffentlichen Nahverkehr umfasst die Aufgaben der Netz-, Linien-,Fahr- und Preisplanung. Wir stellen zwei mathematische Optimierungsmodelle zur Linien- und Preisplanung vor. Wir zeigen anhand von Berechnungen für die Verkehrsbetriebe in Potsdam(ViP), dass sich damit komplexe Zusammenhänge quantitativ analysieren lassen. Auf diese Weise untersuchen wir die Auswirkungen von Freiheitsgraden auf die Konstruktion von Linien und die Wahl von Reisewegen der Passagiere, Abhängigkeiten zwischen Kosten und Reisezeiten sowie den Einfluss verschiedener Preissysteme auf Nachfrage und Kostendeckung. T3 - ZIB-Report - 08-04 KW - Preisplanung KW - Linienplanung KW - Optimierung Y1 - 2008 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-10555 SN - 1438-0064 ER - TY - GEN A1 - Stephan, Rüdiger T1 - On the cardinality constrained matroid polytope N2 - Edmonds showed that the so-called rank inequalities and the nonnegativity constraints provide a complete linear description of the matroid polytope. By essentially adding Grötschel's cardinality forcing inequalities, we obtain a complete linear description of the cardinality constrained matroid polytope which is the convex hull of the incidence vectors of those independent sets that have a feasible cardinality. Moreover, we show how the separation problem for the cardinality forcing inequalities can be reduced to that for the rank inequalities. We also give necessary and sufficient conditions for a cardinality forcing inequality to be facet defining. T3 - ZIB-Report - 08-08 KW - Matroid-Polytop KW - Kardinalitätsbeschränkung KW - Separationsalgorithmus KW - Matroid Polytope KW - Cardinality constraints KW - Separation algorithm Y1 - 2008 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-10614 SN - 1438-0064 ER - TY - THES A1 - Bley, Andreas T1 - Routing and Capacity Optimization for IP Networks N2 - This thesis is concerned with dimensioning and routing optimization problems for communication networks that employ a shortest path routing protocol such as OSPF, IS-IS, or RIP. These protocols are widely used in the Internet. With these routing protocols, all end-to-end data streams are routed along shortest paths with respect to a metric of link lengths. The network administrator can configure the routing only by modifying this metric. In this thesis we consider the unsplittable shortest path routing variant, where each communication demand must be sent unsplit through the network. This requires that all shortest paths are uniquely determined. The major difficulties in planning such networks are that the routing can be controlled only indirectly via the routing metric and that all routing paths depend on the same routing metric. This leads to rather complicated and subtle interdependencies among the paths that comprise a valid routing. In contrast to most other routing schemes, the paths for different communication demands cannot be configured independent of each other. Part I of the thesis is dedicated to the relation between path sets and routing metrics and to the combinatorial properties of those path sets that comprise a valid unsplittable shortest path routing. Besides reviewing known approaches to find a compatible metric for a given path set (or to prove that none exists) and discussing some properties of valid path sets, we show that the problem of finding a compatible metric with integer lengths as small as possible and the problem of finding a smallest possible conflict in the given path set are both NP-hard to approximate within a constant factor. In Part II of the thesis we discuss the relation between unsplittable shortest path routing and several other routing schemes and we analyze the computational complexity of three basic unsplittable shortest path routing problems. We show that the lowest congestion that can be obtained with unsplittable shortest path routing may significantly exceed that achievable with other routing paradigms and we prove several non-approximability results for unsplittable shortest path routing problems that are stronger than those for the corresponding unsplittable flow problems. In addition, we derive various polynomial time approximation algorithms for general and special cases of these problems. In Part III of the thesis we finally develop an integer linear programming approach to solve these and more realistic unsplittable shortest path routing problems to optimality. We present alternative formulations for these problems, discuss their strength and computational complexity, and show how to derive strong valid inequalities. Eventually, we describe our implementation of this solution approach and report on the numerical results obtained for real-world problems that came up in the planning the German National Research and Education Networks G-WiN and X-WiN and for several benchmark instances. N2 - Die Arbeit befasst sich mit der Kapazitäts- und Routenplanung für Kommunikationsnetze, die ein kürzeste-Wege Routingprotokoll verwenden. Diese Art von Protokollen ist im Internet weit verbreitet. Bei diesen Routingverfahren wird für jede Verbindung im Netz ein Längenwert festgelegt, diese Längen formen die sogenannte Routingmetrik. Die Routingwege der Kommunikationsbedarfe sind dann die jeweiligen kürzesten Wege bezüglich dieser Metrik. Bei der in der Arbeit untersuchten Variante dieser Routingprotokolle wird zusätzlich verlangt, dass es je Kommunikationsbedarf genau einen eindeutigen kürzesten Weg gibt. Die Schwierigkeit bei der Planung solcher Netze besteht darin, dass sich die Routingwege einerseits nur indirekt über die Routingmetrik beeinflussen lassen, andererseits aber alle Routingwege von der gleichen Metrik abhängen. Dadurch können die Wege verschiedener Kommunikationsanforderungen nicht wie bei anderen Routingverfahren unabhängig voneinander gewählt werden. Im erstem Teil der Arbeit werden der Zusammenhang zwischen gegebenen Wegesystemen und kompatiblen Routingmetriken sowie die Beziehungen der Wege eines zulässigen eindeutige-kürzeste-Wege-Routings untereinander untersucht. Dabei wird unter Anderem gezeigt, dass es NP-schwer ist, eine kompatible Metrik mit kleinstmöglichen Routinglängen zu einem gegebenen Wegesystem zu finden. Es wird auch bewiesen, dass das Finden eines kleinstmöglichen Konfliktes in einem gegebenen Wegesystem, zu dem keine kompatible Metrik existiert, NP-schwer ist. Im zweiten Teil der Arbeit wird die Approximierbarkeit von drei grundlegenden Netz- und Routenplanungsproblemen mit eindeutige-kürzeste-Wege-Routing untersucht. Für diese Probleme werden stärkere Nichtapproximierbarkeitsresultate als für die entsprechenden Einwege-Routing Probleme bewiesen und es werden verschiedene polynomiale Approximationsverfahren für allgemeine und Spezialfälle entworfen. Ausserdem wird die Beziehung zwischen eindeutige-kürzeste-Wege-Routing und anderen Routingverfahren diskutiert. Im dritten und letzten Teil der Arbeit wird ein (gemischt-) ganzzahliger Lösungsansatz für Planungsprobleme mit eindeutige-kürzeste-Wege-Routing vorgestellt. Für die im zweiten Teil diskutierten grundlegenden Netz- und Routenplanungsprobleme werden verschiedene (gemischt-) ganzzahlige lineare Modelle vorgestellt und es wird deren Lösbarkeit und die Stärke ihrer LP Relaxierungen untersucht. Es wird auch gezeigt, wie sich starke gültig Ungleichungen aus den in diesen Modellen enthalten Substrukturen ableiten lassen. Schlielich werden am Ende der Arbeit die Software-Implementierung dieses Lösungsverfahrens für eine praxisrelevante Verallgemeinerung der Planungsprobleme sowie die damit erzielten numerischen Ergebnisse vorgestellt und diskutiert. KW - kombinatorische Optimierung KW - gemischt-ganzzahlige Programmierung KW - kürzeste-Wege Routing KW - Approximationsalgorithmen KW - combinatorial optimization KW - mixed-integer programming KW - shortest path routing KW - approximation algorithms Y1 - 2007 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:kobv:83-opus-15530 SN - 978-3-86727-281-0 ER - TY - THES A1 - Weider, Steffen T1 - Integration of Vehicle and Duty Scheduling in Public Transport N2 - This thesis describes the algorithm IS-OPT that integrates scheduling of vehicles and duties in public bus transit. IS-OPT is the first algorithm which solves integrated vehicle and duty scheduling problems arising in medium sized carriers such that its solutions can be used in daily operations without further adaptions. This thesis is structured as follows: The first chapter highlights mathematical models of the planning process of public transit companies and examines their potential for integrating them with other planning steps. It also introduces descriptions of the vehicle and the duty scheduling problem. Chapter 2 motivates why it can be useful to integrate vehicle and duty scheduling, explains approaches of the literature, and gives an outline of our algorithm IS-OPT. The following chapters go into the details of the most important techniques and methods of IS-OPT: In Chapter 3 we describe how we use Lagrangean relaxation in a column generation framework. Next, in Chapter 4, we describe a variant of the proximal bundle method (PBM) that is used to approximate linear programs occurring in the solution process. We introduce here a new variant of the PBM which is able to utilize inexact function evaluation and the use of epsilon-subgradients. We also show the convergence of this method under certain assumptions. Chapter 5 treats the generation of duties for the duty scheduling problem. This problem is modeled as a resourceconstraint- shortest-path-problem with non-linear side constraints and nearly linear objective function. It is solved in a two-stage approach. At first we calculate lower bounds on the reduced costs of duties using certain nodes by a new inexact label-setting algorithm. Then we use these bounds to speed up a depth-first-search algorithm that finds feasible duties. In Chapter 6 we present the primal heuristic of IS-OPT that solves the integrated problem to integrality. We introduce a new branch-and-bound based heuristic which we call rapid branching. Rapid branching uses the proximal bundle method to compute lower bounds, it introduces a heuristic node selection scheme, and it utilizes a new branching rule that fixes sets of many variables at once. The common approach to solve the problems occurring in IS-OPT is to trade inexactness of the solutions for speed of the algorithms. This enables, as we show in Chapter 7, to solve large real world integrated problems by IS-OPT. The scheduled produced by IS-OPT save up to 5% of the vehicle and duty cost of existing schedules of regional and urban public transport companies. N2 - Diese Arbeit beschreibt den Algorithmus IS-OPT, welcher der erste Algorithmus ist, der integrierte Umlauf- und Dienstplanungsprobleme für mittelgroße Verkehrsunternehmen löst und dabei alle betrieblichen Einzelheiten berücksichtigt. Seine Lösungen können daher direkt in den täglichen Betrieb übernommen werden. Im ersten Kapitel werden mathematische Modelle für verschiedenen Probleme aus dem Planungsprozess von Nahverkehrsunternehmen beschrieben. Es werden Ansätze zur Integration der einzelnen Probleme untersucht. In diesem Kapitel werden außerdem das Umlauf- und das Dienstplanungsproblem eingeführt. Kapitel 2 motiviert, warum Integration von Umlauf- und Dienstplanung hilfreich ist oder in welchen Fällen sie sogar unabdingbar ist; es gibt einen Überblick über die vorhanden Literatur zur integrierten Umlauf- und Dienstplanung und umreißt unseren Algorithmus IS-OPT. Die weiteren Kapitel behandeln die in IS-OPT verwendeten Methoden: In Kapitel 3 beschreiben wir, wie Spaltenerzeugung für lineare Programme mit Lagrange-Relaxierung und Subgradienten-Verfahren kombiniert werden kann. In Kapitel 4 wird unsere Variante der proximalen Bündelmethode beschrieben. Diese wird benutzt um näherungsweise primale und duale Lösungen von lineare Programmen zu berechnen. Unsere Variante ist angepasst, um auch mit ungenauer Funktionsauswertung und Epsilon-Subgradienten arbeiten zu können. Wir zeigen die Konvergenz dieser Variante unter bestimmten Annahmen. Kapitel 5 behandelt das Erzeugen von Diensten für das Dienstplanungsproblem. Dieses Problem ist als ein Kürzeste-Wege-Problem mit nichtlinearen Nebenbedingungen und fast linearer Zielfunktion modelliert. Wir lösen es, indem zuerst Schranken für die reduzierten Kosten von Diensten, die bestimmte Knoten benutzen, berechnet werden. Diese Schranken werden benutzt, um in einem Tiefensuchalgorithmus den Suchbaum klein zu halten. Im Kapitel 6 präsentieren wir die neu entwickelte Heuristik "Rapid Branching", die eine ganzzahlige Lösung des integrierten Problems berechnet. Rapid Branching kann als eine spezielle Branch-and-Bound-Heuristik gesehen werden, welche die Bündelmethode benutzt. In den Knoten des Suchbaums können mehrere Variablen auf einmal fixiert werden, die mit Hilfe einer Perturbationsheuristik ausgewählt werden. In Kapitel 7 schließlich zeigen wir, daß wir mit IS-OPT auch große Probleminstanzen aus der Praxis lösen können und dabei bis zu 5% der Fahrzeug- und Dienstkosten sparen können. KW - Öffentlicher Personennahverkehr KW - lineare Optimierung KW - Umlaufplanung KW - Dienstplanung KW - Integration KW - Public Transport KW - linear Optimization KW - vehicle scheduling KW - duty scheduling KW - integration Y1 - 2007 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:kobv:83-opus-16240 ER - TY - GEN A1 - Achterberg, Tobias A1 - Berthold, Timo A1 - Koch, Thorsten A1 - Wolter, Kati T1 - Constraint Integer Programming: a New Approach to Integrate CP and MIP N2 - This article introduces constraint integer programming (CIP), which is a novel way to combine constraint programming (CP) and mixed integer programming (MIP) methodologies. CIP is a generalization of MIP that supports the notion of general constraints as in CP. This approach is supported by the CIP framework SCIP, which also integrates techniques from SAT solving. SCIP is available in source code and free for non-commercial use. We demonstrate the usefulness of CIP on two tasks. First, we apply the constraint integer programming approach to pure mixed integer programs. Computational experiments show that SCIP is almost competitive to current state-of-the-art commercial MIP solvers. Second, we employ the CIP framework to solve chip design verification problems, which involve some highly non-linear constraint types that are very hard to handle by pure MIP solvers. The CIP approach is very effective here: it can apply the full sophisticated MIP machinery to the linear part of the problem, while dealing with the non-linear constraints by employing constraint programming techniques. T3 - ZIB-Report - 08-01 KW - Constraint Programming KW - Ganzzahlige Programmierung KW - Branch-And-Cut KW - Optimierungssoftware KW - Chipverifikation KW - constraint programming KW - mixed integer programming KW - branch-and-cut KW - optimization software KW - chip verification Y1 - 2008 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-10520 SN - 1438-0064 ER - TY - GEN A1 - Bley, Andreas T1 - Routing and Capacity Optimization for IP networks N2 - This article describes the main concepts and techniques that have been developed during the last year at ZIB to solve dimensioning and routing optimization problems for IP networks. We discuss the problem of deciding if a given path set corresponds to an unsplittable shortest path routing, the fundamental properties of such path sets, and the computational complexity of some basic network planning problems for this routing type. Then we describe an integer-linear programming approach to solve such problems in practice. This approach has been used successfully in the planning of the German national education and research network for several years. T3 - ZIB-Report - 07-33 KW - kombinatorische Optimierung KW - gemischt-ganzzahlige Programmierung KW - kürzeste-Wege Routing KW - Approximationsalgorithmen KW - combinatorial optimization KW - mixed-integer programming KW - shortest path routing KW - approximation algorithms Y1 - 2007 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-10323 SN - 1438-0064 ER - TY - GEN A1 - Berthold, Timo T1 - Heuristics of the Branch-Cut-and-Price-Framework SCIP N2 - In this paper we give an overview of the heuristics which are integrated into the open source branch-cut-and-price-framework SCIP. We briefly describe the fundamental ideas of different categories of heuristics and present some computational results which demonstrate the impact of heuristics on the overall solving process of SCIP. T3 - ZIB-Report - 07-30 KW - Primalheuristiken KW - Gemischt-Ganzzahlige Programmierung KW - Branch and Cut KW - SCIP KW - mixed integer programming KW - primal heuristics KW - branch and cut KW - SCIP Y1 - 2007 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-10280 SN - 1438-0064 ER - TY - THES A1 - Berthold, Timo T1 - Primal Heuristics for Mixed Integer Programs N2 - A lot of problems arising in Combinatorial Optimization and Operations Research can be formulated as Mixed Integer Programs (MIP). Although MIP-solving is an NP-hard optimization problem, many practically relevant instances can be solved in reasonable time. In modern MIP-solvers like the branch-cut-and-price-framework SCIP, primal heuristics play a major role in finding and improving feasible solutions at the early steps of the solution process. This helps to reduce the overall computational effort, guides the remaining search process, and proves the feasibility of the MIP model. Furthermore, a heuristic solution with a small gap to optimality often is sufficient in practice. We investigate 16 different heuristics, all of which are available in SCIP. Four of them arise from the literature of the last decade, nine are specific implementations of general heuristic ideas, three have been newly developed. We present an improved version of the feasibility pump heuristic by Fischetti et al., which in experiments produced solutions with only a third of the optimality gap compared to the original version. Furthermore, we introduce two new Large Neighborhood Search (LNS) heuristics. Crossover is an LNS improvement heuristic making use of similarities of diverse MIP solutions to generate new incumbent solutions. RENS is an LNS rounding heuristic which evaluates the space of all possible roundings of a fractional LP-solution. This heuristic makes it possible to determine whether a point can be rounded to an integer solution and which is the best possible rounding. We conclude with a computational comparison of all described heuristics. It points out that a single heuristic on its own has only a slight impact on the overall performance of SCIP, but the combination of all of them reduces the running time by a factor of two compared to a version without any heuristics. Y1 - 2006 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-10293 ER - TY - GEN A1 - Borndörfer, Ralf A1 - Grötschel, Martin A1 - Lukac, Sascha A1 - Mitusch, Kay A1 - Schlechte, Thomas A1 - Schultz, Sören A1 - Tanner, Andreas T1 - An Auctioning Approach to Railway Slot Allocation N2 - We present an approach to implement an auction of railway slots. Railway network, train driving characteristics, and safety requirements are described by a simplified, but still complex macroscopic model. In this environment, slots are modelled as combinations of scheduled track segments. The auction design builds on the iterative combinatorial auction. However, combinatorial bids are restricted to some types of slot bundles that realize positive synergies between slots. We present a bidding language that allows bidding for these slot bundles. An integer programming approach is proposed to solve the winner determination problem of our auction. Computational results for auction simulations in the Hannover-Fulda-Kassel area of the German railway network give evidence that auction approaches can induce a more efficient use of railway capacity. T3 - ZIB-Report - 05-45 KW - Railway Slot Allocation KW - Train Dispatching KW - Combinatorial Auctions Y1 - 2005 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-8786 ER - TY - GEN A1 - Borndörfer, Ralf A1 - Karbstein, Marika T1 - Metric Inequalities for Routings on Direct Connections with Application in Line Planning N2 - We consider multi-commodity flow problems in which capacities are installed on paths. In this setting, it is often important to distinguish between flows on direct connection routes, using single paths, and flows that include path switching. We derive a feasibility condition for path capacities supporting such direct connection flows similar to the feasibility condition for arc capacities in ordinary multi-commodity flows. The concept allows to solve large-scale real-world line planning problems in public transport including a novel passenger routing model that favors direct connections over connections with transfers. T3 - ZIB-Report - 15-07 KW - combinatorial optimization KW - integer programming KW - line planning KW - transfers KW - direct connection KW - metric inequalities Y1 - 2015 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-53507 SN - 1438-0064 ER - TY - GEN A1 - Kaibel, Volker A1 - Stephan, Rüdiger T1 - On cardinality constrained cycle and path polytopes N2 - We consider polytopes associated with cardinality constrained path and cycle problems defined on a directed or undirected graph. We present integer characterizations of these polytopes by facet defining linear inequalities for which the separation problem can be solved in polynomial time. Moreover, we give further facet defining inequalities, in particular those that are specific to odd/even paths and cycles. T3 - ZIB-Report - 07-25 KW - path KW - cycles KW - integer characterizations KW - facets Y1 - 2007 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-10093 SN - 1438-0064 ER - TY - GEN A1 - Borndörfer, Ralf A1 - Schlechte, Thomas T1 - Models for Railway Track Allocation N2 - This article is about the optimal track allocation problem (OPTRA) to find, in a given railway network, a conflict free set of train routes of maximum value. We study two types of integer programming formulations: a standard formulation that models block conflicts in terms of packing constraints, and a new extended formulation that is based on additional configuration' variables. We show that the packing constraints in the standard formulation stem from an interval graph, and that they can be separated in polynomial time. It follows that the LP relaxation of a strong version of this model, including all clique inequalities from block conflicts, can be solved in polynomial time. We prove that the extended formulation produces the same LP bound, and that it can also be computed with this model in polynomial time. Albeit the two formulations are in this sense equivalent, the extended formulation has advantages from a computational point of view, because it features a constant number of rows and is therefore amenable to standard column generation techniques. Results of an empirical model comparison on mesoscopic data for the Hannover-Fulda-Kassel region of the German long distance railway network are reported. T3 - ZIB-Report - 07-02 KW - Railway Slot Allocation KW - Train Timetabling KW - Combinatorial Optimization KW - Linear and Integer Programming Y1 - 2007 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-9451 ER - TY - GEN A1 - Borndörfer, Ralf A1 - Schlechte, Thomas T1 - Solving Railway Track Allocation Problems N2 - The \emph{optimal track allocation problem} (\textsc{OPTRA}), also known as the train routing problem or the train timetabling problem, is to find, in a given railway network, a conflict-free set of train routes of maximum value. We propose a novel integer programming formulation for this problem that is based on additional configuration' variables. Its LP-relaxation can be solved in polynomial time. These results are the theoretical basis for a column generation algorithm to solve large-scale track allocation problems. Computational results for the Hanover-Kassel-Fulda area of the German long distance railway network involving up to 570 trains are reported. T3 - ZIB-Report - 07-20 KW - railway track allocation KW - timetabling KW - column generation Y1 - 2007 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-9631 SN - 1438-0064 ER - TY - GEN A1 - Borndörfer, Ralf A1 - Neumann, Marika T1 - Linienoptimierung - reif für die Praxis? N2 - Wir stellen in dieser Arbeit ein mathematisches Optimierungsmodell zur Bestimmung eines optimalen Linienplans vor, das sowohl die Fahrzeiten und die Anzahl der Umstiege berücksichtigt als auch die Kosten des Liniennetzes. Dieses Modell deckt wichtige praktische Anforderungen ab, die in einem gemeinsamen Projekt mit den Verkehrsbetrieben in Potsdam (ViP) formuliert wurden. In diesem Projekt wurde der Linienplan 2010 für Potsdam entwickelt. Unsere Berechnungen zeigen, dass die mathematische Optimierung in nichts einer "Handplanung" des Liniennetzes nachsteht. Im Gegenteil, mit Hilfe des Optimierungsprogramms ist es möglich, durch Veränderung der Parameter mehrere verschiedene Szenarien zu berechnen, miteinander zu vergleichen und Aussagen über minimale Kosten und Fahrzeiten zu machen. T3 - ZIB-Report - 10-20 KW - Linienplanung KW - Optimierung Y1 - 2010 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-11832 SN - 1438-0064 ER - TY - GEN A1 - Hoppmann, Heide T1 - An Extended Formulation for the Line Planning Problem N2 - In this paper we present a novel extended formulation for the line planning problem that is based on what we call “configurations” of lines and frequencies. Configurations account for all possible options to provide a required transportation capacity on an infrastructure edge. The proposed configuration model is strong in the sense that it implies several facet-defining inequalities for the standard model: set cover, symmetric band, MIR, and multicover inequalities. These theoretical findings can be confirmed in computational results. Further, we show how this concept can be generalized to define configurations for subsets of edges; the generalized model implies additional inequalities from the line planning literature. T3 - ZIB-Report - 16-08 KW - Line Planning, Extended Formulation, Public Transport Y1 - 2016 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-57467 SN - 1438-0064 ER - TY - GEN A1 - Berthold, Timo A1 - Heinz, Stefan A1 - Vigerske, Stefan T1 - Extending a CIP framework to solve MIQCPs N2 - This paper discusses how to build a solver for mixed integer quadratically constrained programs (MIQCPs) by extending a framework for constraint integer programming (CIP). The advantage of this approach is that we can utilize the full power of advanced MIP and CP technologies. In particular, this addresses the linear relaxation and the discrete components of the problem. For relaxation, we use an outer approximation generated by linearization of convex constraints and linear underestimation of nonconvex constraints. Further, we give an overview of the reformulation, separation, and propagation techniques that are used to handle the quadratic constraints efficiently. We implemented these methods in the branch-cut-and-price framework SCIP. Computational experiments indicates the potential of the approach. T3 - ZIB-Report - 09-23 KW - mixed integer quadratically constrained programming KW - constraint integer programming KW - convex relaxation KW - nonconvex Y1 - 2009 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-11371 SN - 1438-0064 ER - TY - GEN A1 - Borndörfer, Ralf A1 - Cardonha, Carlos T1 - A Set Partitioning Approach to Shunting N2 - The Vehicle Positioning Problem (VPP) is a classical combinatorial optimization problem in public transport planning. A number of models and approaches have been suggested in the literature, which work for small problems, but not for large ones. We propose in this article a novel set partitioning model and an associated column generation solution approach for the VPP. The model provides a tight linear description of the problem. The pricing problem, and hence the LP relaxation itself, can be solved in polynomial resp. pseudo-polynomial time for some versions of the problems. T3 - ZIB-Report - 09-18 KW - integer programming KW - set partitioning KW - combinatorial packing KW - vehicle positioning Y1 - 2009 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-11326 SN - 1438-0064 ER - TY - GEN A1 - Bley, Andreas T1 - On the Hardness of Finding Small Shortest Path Routing Conflicts N2 - Nowadays most data networks use shortest path protocols such as OSPF or IS-IS to route traffic. Given administrative routing lengths for the links of a network, all data packets are sent along shortest paths with respect to these lengths from their source to their destination. One of the most fundamental problems in planning shortest path networks is to decide whether a given set of routing paths forms a valid routing and, if this is not the case, to find a small subset of the given paths that cannot be shortest paths simultaneously for any routing lengths. In this paper we show that it is NP-hard to approximate the size of the smallest shortest path conflict by a factor less than 7/6. T3 - ZIB-Report - 09-15 KW - shortest path routing KW - computational complexity Y1 - 2009 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-11276 SN - 1438-0064 ER - TY - GEN A1 - Borndörfer, Ralf A1 - Neumann, Marika A1 - Pfetsch, Marc T1 - The Steiner Connectivity Problem N2 - The Steiner connectivity problem is a generalization of the Steiner tree problem. It consists in finding a minimum cost set of simple paths to connect a subset of nodes in an undirected graph. We show that polyhedral and algorithmic results on the Steiner tree problem carry over to the Steiner connectivity problem, namely, the Steiner cut and the Steiner partition inequalities, as well as the associated polynomial time separation algorithms, can be generalized. Similar to the Steiner tree case, a directed formulation, which is stronger than the natural undirected one, plays a central role. T3 - ZIB-Report - 09-07 KW - Steiner Tree KW - Partition Inequalities KW - Paths KW - Connectivity KW - Generalization Y1 - 2009 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-11171 SN - 1438-0064 ER - TY - GEN A1 - Torres, Luis Miguel A1 - Torres, Ramiro A1 - Borndörfer, Ralf A1 - Pfetsch, Marc T1 - Line Planning on Paths and Tree Networks with Applications to the Quito Trolebus System (Extended Abstract) N2 - Line planning is an important step in the strategic planning process of a public transportation system. In this paper, we discuss an optimization model for this problem in order to minimize operation costs while guaranteeing a certain level of quality of service, in terms of available transport capacity. We analyze the problem for path and tree network topologies as well as several categories of line operation that are important for the Quito Trolebus system. It turns out that, from a computational complexity worst case point of view, the problem is hard in all but the most simple variants. In practice, however, instances based on real data from the Trolebus System in Quito can be solved quite well, and significant optimization potentials can be demonstrated. T3 - ZIB-Report - 08-53 KW - line planning KW - computational complexity KW - public transport KW - integer programming Y1 - 2008 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-11076 SN - 1438-0064 ER - TY - GEN A1 - Torres, Luis Miguel A1 - Torres, Ramiro A1 - Borndörfer, Ralf A1 - Pfetsch, Marc T1 - On the Line Planning Problem in Tree Networks N2 - We introduce an optimization model for the line planning problem in a public transportation system that aims at minimizing operational costs while ensuring a given level of quality of service in terms of available transport capacity. We discuss the computational complexity of the model for tree network topologies and line structures that arise in a real-world application at the Trolebus Integrated System in Quito. Computational results for this system are reported. T3 - ZIB-Report - 08-52 KW - line planning KW - computational complexity KW - public transport optimization Y1 - 2008 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-11069 SN - 1438-0064 ER - TY - GEN A1 - Torres, Luis Miguel A1 - Torres, Ramiro A1 - Borndörfer, Ralf A1 - Pfetsch, Marc T1 - Line Planning on Paths and Tree Networks with Applications to the Quito Trolebus System N2 - Line planning is an important step in the strategic planning process of a public transportation system. In this paper, we discuss an optimization model for this problem in order to minimize operation costs while guaranteeing a certain level of quality of service, in terms of available transport capacity. We analyze the problem for path and tree network topologies as well as several categories of line operation that are important for the Quito Trolebus system. It turns out that, from a computational complexity worst case point of view, the problem is hard in all but the most simple variants. In practice, however, instances based on real data from the Trolebus System in Quito can be solved quite well, and significant optimization potentials can be demonstrated. T3 - ZIB-Report - 08-35 KW - line planning KW - computational complexity KW - public transport KW - integer programming Y1 - 2008 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-10869 SN - 1438-0064 ER - TY - GEN A1 - Stephan, Rüdiger T1 - Cardinality Constrained Combinatorial Optimization: Complexity and Polyhedra N2 - Given a combinatorial optimization problem and a subset $N$ of natural numbers, we obtain a cardinality constrained version of this problem by permitting only those feasible solutions whose cardinalities are elements of $N$. In this paper we briefly touch on questions that addresses common grounds and differences of the complexity of a combinatorial optimization problem and its cardinality constrained version. Afterwards we focus on polytopes associated with cardinality constrained combinatorial optimization problems. Given an integer programming formulation for a combinatorial optimization problem, by essentially adding Grötschel's cardinality forcing inequalities, we obtain an integer programming formulation for its cardinality restricted version. Since the cardinality forcing inequalities in their original form are mostly not facet defining for the associated polyhedra, we discuss possibilities to strengthen them. T3 - ZIB-Report - 08-48 KW - Combinatorial Optimization KW - Cardinality Constraints KW - Matroids KW - Cardinality Forcing Inequalities Y1 - 2008 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-11026 SN - 1438-0064 ER - TY - THES A1 - Krumke, Sven T1 - Online Optimization: Competitive Analysis and Beyond N2 - Traditional optimization techniques assume, in general, knowledge of all data of a problem instance. There are many cases in practice, however, where decisions have to be made before complete information about the data is available. In fact, it may be necessary to produce a part of the problem solution as soon as a new piece of information becomes known. This is called an \emph{online situation}, and an algorithm is termed \emph{online}, if it makes a decision (computes a partial solution) whenever a new piece of data requests an action. \emph{Competitive analysis} has become a standard yardstick to measure the quality of online algorithms. One compares the solution produced by an online algorithm to that of an optimal (clairvoyant) offline algorithm. An online algorithm is called $c$-competitive if on every input the solution it produces has cost'' at most $c$~times that of the optimal offline algorithm. This situation can be imagined as a game between an online player and a malicious adversary. Although competitive analysis is a worst-case analysis and henceforth pessimistic, it often allows important insights into the problem structure. One can obtain an idea about what kind of strategies are promising for real-world systems and why. On the other hand there are also cases where the offline adversary is simply too powerful and allows only trivial competitiveness results. This phenomenon is called hitting the triviality barrier''. We investigate several online problems by means of competitive analysis. We also introduce new concepts to overcome the weaknesses of the standard approach and to go beyond the triviality barrier. T3 - ZIB-Report - 02-25 KW - competitive analysis KW - online optimization KW - online algorithm KW - approximation algorithm Y1 - 2002 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-6925 ER - TY - GEN A1 - Borndörfer, Ralf T1 - Combinatorial Packing Problems N2 - This article investigates a certain class of combinatorial packing problems and some polyhedral relations between such problems and the set packing problem. T3 - ZIB-Report - 03-03 KW - Packing problems KW - polyhedral combinatorics Y1 - 2003 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-7255 ER - TY - GEN A1 - Gamrath, Gerald A1 - Koch, Thorsten A1 - Rehfeldt, Daniel A1 - Shinano, Yuji T1 - SCIP-Jack - A massively parallel STP solver N2 - In this article we describe the impact from embedding a 15 year old model for solving the Steiner tree problem in graphs in a state-of-the-art MIP-Framework, making the result run in a massively parallel environment and extending the model to solve as many variants as possible. We end up with a high-perfomance solver that is capable of solving previously unsolved instances and, in contrast to its predecessor, is freely available for academic research. T3 - ZIB-Report - 14-35 KW - Steiner Tree Problem KW - Mixed-Integer Programming KW - Branch-and-Cut KW - DIMACS Challenge Y1 - 2014 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-52293 SN - 1438-0064 ER - TY - GEN A1 - Heismann, Olga A1 - Borndörfer, Ralf T1 - A Generalization of Odd Set Inequalities for the Set Packing Problem N2 - The set packing problem, sometimes also called the stable set problem, is a well-known NP-hard problem in combinatorial optimization with a wide range of applications and an interesting polyhedral structure, that has been the subject of intensive study. We contribute to this field by showing how, employing cliques, odd set inequalities for the matching problem can be generalized to valid inequalities for the set packing polytope with a clear combinatorial meaning. T3 - ZIB-Report - 14-28 KW - set packing KW - matching KW - hypergraph KW - inequality KW - facet Y1 - 2014 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-51010 SN - 1438-0064 ER - TY - GEN A1 - Borndörfer, Ralf A1 - Hoppmann, Heide A1 - Karbstein, Marika T1 - Passenger Routing for Periodic Timetable Optimization N2 - The task of periodic timetabling is to schedule the trips in a public transport system by determining arrival and departure times at every station such that travel and transfer times are minimized. To date, the optimization literature generally assumes that passengers do not respond to changes in the timetable, i.e., the passenger routes are fixed. This is unrealistic and ignores potentially valuable degrees of freedom. We investigate in this paper periodic timetabling models with integrated passenger routing. We show that different routing models have a huge influence on the quality of the entire system: Whatever metric is applied, the performance ratios of timetables w.r.t. to different routing models can be arbitrarily large. Computations on a real-world instance for the city of Wuppertal substantiate the theoretical findings. These results indicate the existence of untapped optimization potentials that can be used to improve the efficiency of public transport systems. T3 - ZIB-Report - 15-55 KW - Passenger routing KW - Periodic timetabling KW - Public transport Y1 - 2015 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-56739 SN - 1438-0064 ER - TY - GEN A1 - Borndörfer, Ralf A1 - Hoppmann, Heide A1 - Karbstein, Marika T1 - Timetabling and Passenger Routing in Public Transport T2 - Appeard in: Proceedings of Conference on Advanced Systems in Public Transport 2015 (CASPT2015) N2 - The task of timetabling is to schedule the trips in a public transport system by determining periodic arrival and departure times at every station. The goal is to provide a service that is both attractive for passengers and can be operated economically. To date, timetable optimization is generally done with respect to fixed passenger routes, i.e., it is assumed that passengers do not respond to changes in the timetable. This is unrealistic and ignores potentially valuable degrees of freedom. We investigate in this paper periodic timetabling models with integrated passenger routing. We propose several models that differ in the allowed passenger paths and the objectives. We compare these models theoretically and report on computations on real-world instances for the city of Wuppertal. T3 - ZIB-Report - 15-31 KW - Passenger routing KW - Periodic timetabling KW - Public transport Y1 - 2015 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-55305 SN - 1438-0064 ER - TY - GEN A1 - Borndörfer, Ralf A1 - Hoppmann, Heide A1 - Karbstein, Marika T1 - Umsteigen ohne Warten N2 - Wir stellen einen mathematischen Optimierungsansatz zur Berechnung von periodischen Taktfahrplänen vor, bei dem die Umsteigezeiten unter Berücksichtigung des Passagierverhaltens minimiert werden. Wir untersuchen damit den Einfluss wichtiger Systemparameter und Verhaltensmuster auf die Beförderungsqualität. T3 - ZIB-Report - 17-05 Y1 - 2017 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-62006 SN - 1438-0064 ER - TY - GEN A1 - Karbstein, Marika T1 - Integrated Line Planning and Passenger Routing: Connectivity and Transfers N2 - The integrated line planning and passenger routing problem is an important planning problem in service design of public transport. A major challenge is the treatment of transfers. A main property of a line system is its connectivity. In this paper we show that analysing the connecvitiy aspect of a line plan gives a new idea to handle the transfer aspect of the line planning problem. T3 - ZIB-Report - 14-42 KW - line planning, transfers,Steiner connectivity problem Y1 - 2014 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-52986 SN - 1438-0064 ER - TY - GEN A1 - Bortoletto, Enrico A1 - Lindner, Niels A1 - Masing, Berenike T1 - The Tropical and Zonotopal Geometry of Periodic Timetables N2 - The Periodic Event Scheduling Problem (PESP) is the standard mathematical tool for optimizing periodic timetabling problems in public transport. A solution to PESP consists of three parts: a periodic timetable, a periodic tension, and integer periodic offset values. While the space of periodic tension has received much attention in the past, we explore geometric properties of the other two components, establishing novel connections between periodic timetabling and discrete geometry. Firstly, we study the space of feasible periodic timetables, and decompose it into polytropes, i.e., polytopes that are convex both classically and in the sense of tropical geometry. We then study this decomposition and use it to outline a new heuristic for PESP, based on the tropical neighbourhood of the polytropes. Secondly, we recognize that the space of fractional cycle offsets is in fact a zonotope. We relate its zonotopal tilings back to the hyperrectangle of fractional periodic tensions and to the tropical neighbourhood of the periodic timetable space. To conclude we also use this new understanding to give tight lower bounds on the minimum width of an integral cycle basis. T3 - ZIB-Report - 22-09 KW - periodic event scheduling KW - tropical geometry KW - zonotopal tilings Y1 - 2022 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-86708 SN - 1438-0064 ER - TY - GEN A1 - Borndörfer, Ralf A1 - Danecker, Fabian A1 - Weiser, Martin T1 - A Discrete-Continuous Algorithm for Free Flight Planning N2 - We propose a hybrid discrete-continuous algorithm for flight planning in free flight airspaces. In a first step, our DisCOptER method discrete-continuous optimization for enhanced resolution) computes a globally optimal approximate flight path on a discretization of the problem using the A* method. This route initializes a Newton method that converges rapidly to the smooth optimum in a second step. The correctness, accuracy, and complexity of the method are goverened by the choice of the crossover point that determines the coarseness of the discretization. We analyze the optimal choice of the crossover point and demonstrate the asymtotic superority of DisCOptER over a purely discrete approach. T3 - ZIB-Report - 20-33 KW - shortest path KW - flight planning KW - free flight KW - discrete-continuous algorithm KW - optimal control KW - discrete optimization Y1 - 2020 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:0297-zib-81343 SN - 1438-0064 ER -