Effect of different inspection strategies on the reliability of Daniels systems subjected to fatigue
(2013)
Updating of fatigue reliability with inspection data using subset simulation - problems encountered
(2013)
In this presentation, we discuss the potential of probabilistic approaches to the design and assessment of offshore foundations. The potential is demonstrated in a numerical example considering a laterally loaded monopile. As an outlook, we present a concept for managing the risk associated with installing large monopiles.
In this presentation, a framework for integrating vibration-based structural health monitoring data into the optimization of inspection and maintenance of deteriorating structural systems is presented. The framework is demonstrated in an illustrative example considering a steel frame subject to fatigue.
Im AISTEC Projekt erforscht der FB 7.2 Verfahren zur Bewertung von Verkehrsbrücken auf der Gruandlage von sensorbasierten Bauwerksmessungen. In diesem Vortrag wird ein Überlick über die Forschungsarbeiten des FB 7.2 präsentiert. Des Weiteren wird ein Ausblick zur quantitativen Integration von sensorbasierten Bauwerksmessungen in die risiko-basierte prädiktive Planung von Inspektionen und Reparaturen von Ingenieurbauwerken gegeben.
Fatigue is one of the main deterioration processes affecting the performance of welded steel support structures of wind turbines in offshore wind farms. In this contribution, we present a probabilistic physics-based fatigue deterioration model of a wind farm that accounts for the stochastic dependence among the fatigue behavior of different hotspots at turbine and wind farm level. The dependence exists because of uncertain common influencing factors such as similar material properties, fabrication qualities and load conditions. These system effects signify that an inspection of one hotspot provides indirect information of the condition of the remaining hotspots and thus enable an optimization of the inspection effort for a wind farm.
The wind farm model consists of two levels: A turbine support structure (level 1 system model) is represented by its fatigue hotspots and their stochastic dependence. The fatigue performance of a hotspot is described by a probabilistic fracture mechanics (FM) fatigue model. The probabilistic model of the parameters of the FM fatigue model is calibrated based on design data and is thus directly linked to the design of the turbine support structures. Dependence among the fatigue performances of different hotspots in a turbine support structure is modeled by introducing correlations between the stochastic parameters of the FM fatigue models. A wind farm (level 2 system model) consists of different turbine support structures (level 1 system models). Additional correlations are introduced at wind farm level to account for the dependence among the fatigue behavior of hotspots belonging to different turbine support structures. The wind farm model enables the computation of (marginal) hotspot fatigue reliabilities, system fatigue reliabilities of individual turbine support structures and the system fatigue reliability of an entire wind farm. The probabilistic model of the parameters of the two-level system model can be consistently updated with inspection outcomes using Bayesian methods. The updated probabilistic model of the model parameters then forms the basis for updating the estimates of the fatigue reliabilities.
We implement the wind farm model in a software tool named SysPark. The tool provides the means for planning inspections at wind farm level using an adaptive reliability-based threshold approach. In this approach, the first inspection campaign is planned in the year before the fatigue failure rates of the hotspots with the lowest fatigue reliabilities exceed a threshold failure rate. Once inspection results become available, the probabilistic model of the parameters of the wind farm model is updated. If repairs are performed, the wind farm model is additionally modified to describe the behavior of the repaired hotspots. The updated and modified model then enables the planning of the next inspection campaign and so on. The software tool is demonstrated in a case study considering a generic wind farm consisting of turbines with jacket support structures.